Draw Scores

Job Completed vs Funds Disbursed

Gap Before Draw = 8%
15% Completed
23% Funded
Gap After Draw = 7%
20% Completed
27% Funded

Draw Request #3

20% Job Complete

$23,500 of $398,286

Draw Request #3 Breakdown

Milestone Checkpoints Invoice Amount Rating % Complete

Change order 1

Demo garage slab - Rate = 4

Excavate/ underpin footings - Rate = 4

Demo footing - Rate = 4

Cut footing - Rate = 4

Relocate rebar, footing and forms - Rate = 4

Excavate soil - Rate = 4

 

$23,500

4

5%

Funds Overview

Lender Funded
Original
$374,786
Total Change Orders
$23,500
Total Disbursed
-$85,270.26
Balance
$313,016

People

Name License Insurance Workers Comp Notes

Todd Zaionz Construction

🟢

🟢

🟢

N/A

Draw Request History

Draw Request Total General Contractor Sub Contractor Invoice(s) Lien Waiver Images Receipt

Draw Request #3

$23,500

$23,500

$0

🧾

Draw Request #2

$41,152.26

$41,152.26

$0

🧾

Draw Request #1

$44,118

$44,118

$0

N/A

N/A

🧾

Draw Request Breakdown

  • Change Order 1 – 5% complete, Rate = 4, Invoice amount = $23,500
  • Demo existing garage slab – Rate = 4
  • Excavate/ underpin footing  – Rate = 4. 
  • Demo footing- Rate = 4
  • Cut footing – Rate = 4
  • Relocate rebar, footing and form – Rate =4
  • Excavate soil – Rate = 4
  • Site Prep –
    1% complete, Rate = 4.5, Invoice amount = $3,000
    Code Inspection – confirmed
    Dig Footings – Rate = 4.5
    Shoring – Rate = 4.5
  • Demo –
    2.5% complete, Rate = 3.5
    Disconnect/ Cap off – rate = 3.5
    Pre-demolition -confirmed
  • Forms/ Foundation
    7% complete, Rate= 4.5, Invoice amount = $24,576.13
    Forms, Steel, anchor bolts, hold down bolts – Rate= 4.5
    Code inspection – confirmed
    Confirm order for concrete pour – confirmed
  • Structural Steel – 4% complete, rate = 4, Invoice amount = $13,576.13
    Install review – Rate=4
    Code Inspection – confirmed

Deposit for $44,118

Progress by Milestone

Milestone % Completed % Funded Gap Lien Status
Demolition
100%
100%
Closed
Rough Plumbing
15%
18%
3%
Open
Cabinetry
15%
15%
Open
Rough Electrical
12%
14%
2%
Open